B.C. Place completes $185 million upgrade, readying for World Cup with new features.

B.C. Place is ready for the FIFA World Cup — and it looks a little different. The Vancouver stadium has been transformed by renovations totalling up to $185 million, according to The Province. FIFA's own stadium chief called it like "moving into a brand-new house."
Seven matches will be played at B.C. Place starting June 13, 2026, when Australia faces Turkey. The upgrades touch nearly every corner of the 43-year-old stadium — from the grass under players' feet to the signs on the walls.
For the first time since the 2015 Women's World Cup, B.C. Place will host FIFA matches — but on a very different surface. Back in 2015, over 40 players including Abby Wambach sued FIFA for making women play on artificial turf while the men's tournament required grass. Now, FIFA has flipped the script. Natural grass grown in Abbotsford, B.C., was installed on a raised platform 18 inches above the existing turf, according to Vancouver Sun.
The installation took two weeks and finished May 9. B.C. Place General Manager Chris May said FIFA was clear on one thing: "The quality of the pitch is more important than anything." After the World Cup ends, the grass will be removed and the artificial surface will return for tenants like the BC Lions and Vancouver Whitecaps.
Beyond the grass, FIFA made a series of smaller but visible changes. A new gold-themed sign system now guides fans inside and outside the stadium. Section numbers in the bowl have been replaced. Two new VIP hospitality areas — including a space called the "Corner Club" — were built for the tournament, Brantford Expositor reported.
FIFA also plans to keep the stadium's retractable roof closed for all seven matches. May said FIFA will weigh weather, humidity, and wind when making that call. The consistency is intentional — FIFA wants the same experience at every game.
The stadium upgrades are just one piece of a much larger price tag. Total hosting costs for Vancouver have ballooned to as much as $729 million — up from an initial estimate of $240 million to $260 million in 2022, according to Edmonton Examiner. Security alone costs $242 million. The federal government is contributing $116 million for operations and $100 million for security.
Opposition politicians say the NDP government buried a $105 million cost increase by releasing it on a Friday after the legislature closed. B.C. Conservative finance critic Peter Milobar warned that "costs are going to fall on ordinary British Columbians through higher taxes." To help cover city costs, a 2.5% hotel tax was added in 2023 and will stay in place until 2030.
Premier David Eby says the investment will pay off. He called the stadium upgrades a source of "lines of revenue" that are "hard to understate." The province projects $1 billion in visitor spending between 2026 and 2031, with 350,000 spectators expected during the tournament alone. A Leger poll from March 2026 found 74% of British Columbians support hosting the matches.
But that same poll found 65% of residents worried about taxpayer costs. Sports economist Moshe Lander of Concordia University argues the "legacy" benefits from events like this are often overstated. He noted that B.C. Place's downtown location requires expensive security cordons — one reason Vancouver's security budget is nearly triple Toronto's, Hanna Herald reported.